If a slope is described as 3:1 (horizontal:vertical), what is the approximate grade percentage?

Prepare for the NCCER Introduction to Earthmoving Test with questions that mirror the exam. Utilize multiple choice questions, hints, and explanations to gear up for your certification.

Multiple Choice

If a slope is described as 3:1 (horizontal:vertical), what is the approximate grade percentage?

Explanation:
Grade percentage is found by taking the vertical rise and dividing it by the horizontal distance, then multiplying by 100. A 3:1 slope (horizontal:vertical) means for every 3 units of horizontal distance, the elevation rises 1 unit. So the grade is (1/3) × 100% ≈ 33.3%. That’s why the correct choice is about 33.3%. The other numbers come from different rise-to-run ratios and don’t match the 3:1 description.

Grade percentage is found by taking the vertical rise and dividing it by the horizontal distance, then multiplying by 100. A 3:1 slope (horizontal:vertical) means for every 3 units of horizontal distance, the elevation rises 1 unit. So the grade is (1/3) × 100% ≈ 33.3%. That’s why the correct choice is about 33.3%. The other numbers come from different rise-to-run ratios and don’t match the 3:1 description.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy